Technical description:
The boiler have a horizontally arranged welded structure with fire and flue tube scheme and one radiated and two convectional
surface of the passes. The com-bustion chamber is to 5 t/hrs produced steam a smooth fire tube with stiffened rings, above 5
t!hrs produced steam a FOX type corrugated fire tube and joining to the combustion chamber a water-cooled cylindrical return
chamber in the boilers inside. The combus-tion products leave the combus-tion chamber through the convectional smoke tubes of
the second pass into the front return chamber welded to the front end of the boiler. The smoke tubes of the third pass from
those the smoke leave the boiler into the chimney during a flue-collector mounted to the boiler's back end takes one's place
on right and left sides of the smoke tubes of the second pass.
One might to perform the boiler's water-side check and clening during the manholes and the wash-out holes
located at the both side of the boiler casing (or drum). The boiler drum is supported by legs mounted to the base plate. The
boiler's heath insulation is a rock-basic material blanket, the cover of than is an aluminium plate.
The purpose of the boiler:
The steam boilers type AKH suitable for production of saturated steam for heating or for industrial technology
at effective pressure maximum 12, 17 or 22 bar.
The boilers' pipe ends made in normal construction so that one might to built-in the appliances for periodical control delivered
at the same time for demand of the order. One can to carry out the controlless operation use for these appliances by convenient
boiler-feed make-up.
The boilers are working with available burners for gas, light or heavy fuel oil.
The feedwater heaters type TE-... Produced also by same Manufacturer are served for utilization of the smoke energy contents
come out from the boiler, which are suitable for independent placing or for mounting onto the boiler's smoke outlet. One needs
to take a technical agreement with the Manufacturer at the negotiation a contract about its setting-in.
Package:
Boiler drum without packingBurner and parts in a wooden packing-case.
Rough parts without packing.Fine appliances in a wooden packing-case
Term of delivery:
The time of delivery is 1-3 monts counted from the order or signing a contract, a negotiation is possible in case of pressing order.
Warranty:
The warranty is valid till 12 monts from the date of setting into service in 18 monts from the delivery which one should be change according to the contract.
|